Corrugated culverts buried in ordinary soil foundations often experience a certain degree of subsidence after a period of time, and the subsidence is usually greater in the middle of the pipe than at both ends.
Therefore, the corrugated culvert pipes laid under the embankment should have an upward pre-camber in the middle. The pre-camber is determined by a comprehensive consideration of factors such as the potential settlement of the foundation, the longitudinal slope of the culvert bottom, and the height of the fill. It is usually 0.3% to 1% of the pipe length, and the maximum is no more than 2%, to ensure that no depression or landslide occurs in the middle of the pipe.
|
|
|
|
|